|
Axbridge Caving Group |
||
|
Forum Gallery Downloads International Expeditions Digging Links ~ News ~ History |
||
|
Locations Trip Reports Group Documentation Journals VisitorStats |
||
|
Axbridge Caving Group |
||
|
Forum Gallery Downloads International Expeditions Digging Links ~ News ~ History |
||
|
Locations Trip Reports Group Documentation Journals VisitorStats |
||
Last year at an ACG caving meeting, John Dobson
mentioned to me about a Farmer at Loxton, who had a draughting slot on his
ground, which possible could be a cave. He had asked John if the Axbridge
diggers would be interested in looking at the site.
1st July 1999 - Doug Harris, Elaine Johnson, John Chapman
We introduced ourselves to
Mr and Mrs Jay, chatted a little about the cave and how long they had known
about it. Mr Jay then showed the site, which was found, after crossing a field of sheep and another containing a horse. Over a
fence and down into a slight depression, covered in trees, brambles and thick
undergrowth. John Chapman thought it might have been an old mineshaft, which
had been back filled. Before we cleared a path to the entrance I took some
photographs of the site. The entrance roof was curved with moss and algae
stains on the limestone. On removal of a few handfuls of soil a slight draught
could be felt, coming from lower down the back fill. More digging gear and
space to move was needed.
8th July 1999 - Doug Harris
I returned to do a spot of
gardening, or was it jungle clearing, the brambles were an inch thick. After an
hour the area around the entrance was cleared and more photos were taken. Mr
Jay turned up to see how things were going. He helped me shift a few buckets of
soil and rocks from the entrance. A slight cavity was found as the shovel
disappeared up to its handle. The following evening a visit was made to
15th July 1999 - Doug Harris, Elaine Johnson, Dave Watts
The soil was cleared from a
smaller hole to the right of the entrance. Fourteen barrow loads were removed -
far quicker than using the drums. Another tree was felled to improve access for
both the wheelbarrow and its operator. After eighteen inches of digging a
junction was met. The left hand junction turned into an ochre filled pocket
whilst the down right hand junction four feet of tight passage could be seen.
The main entrance roof was sloping down towards the field (South facing).
Animal bones and glass were removed as digging continued. The cave was named
after the landowner as
19th July 1999 - Doug Harris, Elaine Johnson
The tight passage going back
into the hillside was cleared and we noticed horrible smell draughting from the
end of the passage. After removing a large rock I squeezed myself along the
passage, now eight feet long. I could see into a chamber but couldn’t bend
myself around the corner. After removal of more rocks and soil the smell became
more intense. Elaine continued with the digging and more progress was made. It
was 10pm (2 hours of digging had already been done) and as we were keen to make
a breakthrough work continued. I went back in and inched myself around the
corner, peered over a small ledge and came face to face with a large Badger
covered in Maggots, not a pretty sight. Clearing away the soil to the left of
the Badger it could be seen that the chamber was twelve feet long, at an angle
of sixty degrees upslope and about three feet high. A small chimney was also
noticed. Elaine appeared with a camera and more photos were taken.
22nd July 1999 - Doug Harris
I returned and removed six
wheelbarrow loads of soil from the entrance, revealing two small phreatic
tubes.
26th July 1999 - Doug Harris, Elaine Johnson, Hugh Tucker
Twenty barrow loads of soils
was removed from the entrance
2nd August 1999 - Doug Harris, Hugh Tucker, Mick & Kathleen
Norton
Twenty-five barrow loads of
soils was removed from the entrance. The entrance is now getting larger and another three phreatic
tubes have been revealed.
9th August 1999 - Doug Harris, Elaine Johnson, Hugh Tucker
Worked in the chamber
mentioned on 19th July. Elaine carefully removed the Badger plus its
bedding which was buried in the soil pile. Working back at the entrance of the
main dig I felt a strong draught coming from below my feet, from a small hole.
The speed of digging then increased, with soil and rocks going in all
directions. A phreatic tube was located with darkness at the end. Elaine had a
quick peep. Then it happened, I squeezed along the tube and out into a chamber;
small at first but increasing in size. I slid down a loose pile of soil onto a
firm floor of rock, to my right was a neatly stacked pile of deads, made by the
miners. Hugh noticed that the walls were covered in pick marks made by the
ochre miners. A sandy pit was located in the floor. The right hand wall was
scalloped and water wore, but the roof didn’t look too good. There were piles
of shattered/broken limestone on the floor. The chamber measured approximately
sixty foot long, fifteen feet wide and fifteen feet high. No signs of any
formations yet; many photos taken.
10th August 1999 - Doug Harris
Took a sheet of corrugated
iron and some poles to shore up the entrance. On 12th august 1999
Mick and Kathleen found an old miner’s lamp in the soil slope in the new
chamber.
16th August 1999 - Doug Harris, Elaine Johnson, Hugh Tucker, Alan
Gray, Gwen Sawicki, Cliff Dockrell and Terry Seavers (Gwen’s boss, another
gardener)
News of the new find had
spread. Cliff and myself, using a ten feet long iron bar, made a connection
between the entrance and the bottom of the soil infill in the new chamber.
Proved that the miners would have used the now soil blocked entrance to gain
access to the cave and then the ochre deposits.

12th September & 3rd October
1999 - Doug Harris - spoil
removal.
4th October 1999 - Doug Harris, Elaine Johnson, Hugh Tucker, Alan
Gray, Gwen Sawicki, Dave Watts and Terry Seavers
Alan, Elaine and Terry
surveying whilst the others concentrated on removal of spoil from the Badger
Chamber.
17th October 1999 - Doug Harris
A scaffold plank was
installed over the four foot drop into the entrance, which allowed a safer and
easier access out of the small entrance hole leading to the Badger Chamber. The
chamber was cleared of its infill, loose soil and rocks to reveal the ochre
pockets and scalloped walls. Twenty eight drums were removed.
18th October 1999 - Doug Harris, Dave Watts
Removed more drums of rocks
and soil from the floor in Badger Chamber. The floor has now been lowered by
about three feet below the entrance.
The Story So Far!!!!
|
|
Wall
Distance |
Roof Height |
Station Height |
||||||
|
From |
To |
Clinometer |
Tape |
Compass |
|
Station |
Left |
Right |
||
MAIN CHAMBER
|
||||||||||
|
1 |
2 |
- 21° |
3.15m |
240.5° |
|
2 |
0.6m |
0.95m |
1.32m |
0 |
|
2 |
3 |
- 41° |
2.85m |
222° |
|
3 |
0 |
0.60m |
0.25m |
0.25m |
|
3 |
4 |
- 21° |
2.34m |
294° |
|
4 |
1.49m |
0.25m |
1.18m |
0.2m |
|
4 |
5 |
- 19° |
2.56m |
224° |
|
5 |
0.82m |
0.92m |
0 |
1.4m |
|
5 |
6 |
- 32° |
2.95m |
254.5° |
|
6 |
0.95m |
1.25m |
0.72m |
0.72m |
|
6 |
7 |
- 11° |
2.10m |
247° |
|
7 |
0 |
3.0m |
2.14m |
2.35m |
|
7 |
8 |
+8° |
5.47m |
258.5° |
|
8 |
1.84m |
1.74m |
1.35m |
2.67m |
|
7 |
9 |
+9° |
5.12m |
293.5° |
|
9 |
4.51m |
1.4m |
0.3m |
3.24m |
|
|
|
|
|
|
|
|
|
|
|
|
BADGER HOLE
|
||||||||||
|
1 |
2 |
- 21° |
1.88m |
295.5° |
|
2 |
0m |
0.91m |
0.54m |
0.56m |
|
2 |
3 |
- 26° |
1.73m |
51° |
|
3 |
0m |
0.53m |
0.58m |
0.8m |
|
3 |
4 |
+12° |
1.03m |
89.5° |
|
4 |
0.64m |
0.67m |
1.25m |
0.56m |
|
4 |
5 |
+42° |
4.2m |
11.5° |
|
5 |
0.2m |
0.24m |
0.25m |
0.22m |
Clinometer Calibration -
Downhill = -25.5°, Uphill = +24.5°.
Sheet No. - 1 of
Compass Calibration - Junction of
Junction of
